The interim application of EOT from 18 June , 2018 to 15 July 2018

dc.contributor.authorBUCG-ABC Joint Venture
dc.date.accessioned2023-09-04T05:48:28Z
dc.date.available2023-09-04T05:48:28Z
dc.date.issued2018-07-16
dc.descriptionThis record consists of general correspondence regarding the interim application of EOT from 18 June , 2018 to 15 July 201 May of Brac University new campus development project .
dc.identifier.otherRef: BUCG-ABC JV/BRACU/48/18
dc.identifier.otherhttps://dspace.bracu.ac.bd/server/api/core/items/3808a204-4aaf-43e5-b8c3-34ec23bf2661
dc.identifier.urihttp://hdl.handle.net/10361/20494
dc.language.isoen
dc.publisherBrac University
dc.sourceBRAC University Institutional Repository
dc.subjectNew campus project
dc.subjectGeneral correspondence
dc.subjectBUCG-ABC
dc.subjectInterim application
dc.subjectEOT
dc.titleThe interim application of EOT from 18 June , 2018 to 15 July 2018
dc.typeGeneral correspondence